MDW01 - CCS Maintenance Notification - HVAC pumping packages (CH2-DWP-03) (PM Date 2025-12-31 6:00 AM - 2026-01-30 2:00 PM)

Scheduled Maintenance Report for Cirrascale Cloud Services

Completed

The scheduled maintenance has been completed.
Posted Jan 30, 2026 - 14:00 CST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 31, 2025 - 06:00 CST

Scheduled

Dear Customer,

Please be advised of an upcoming scheduled planned maintenance event affecting our MDW (Chicago) Data center:

📅 Date:
Dec 31, 2025 – Jan 30, 2026
⏰ Time:
6:00 AM CST – 2:00 PM CST
📍 Location:
MDW (Chicago)

🔧 Affected Services:

CH2 CH2-DWP-03

⚠️ Expected Impact:
No impact anticipated

What’s Happening?
This Preventative Maintenance will check operation of HVAC pumping packages. It will also require a test of the cooling loops. This maintenance will have an internal notification and will be performed by CCS Data Center Partners.


Annual inspection includes the following:

· All steps performed in quarterly inspection.

· Test changeover operation of pump package.

· Check for proper voltage and amperage draw on pump motors.

· Check electrical connections (tighten as necessary), contacts and fuses.

· Check coolant loop expansion tanks for correct operating pressures.

· Check coolant loop make up tank and pump operation.

How You’ll Be Notified On The Day Of Planned Maintenance:
✅ 1 day before maintenance – Reminder notification
✅ 1 hour before maintenance – Final notification
✅ After completion – "All Clear" message
Need Help?
Our team will actively monitor the situation and remain in contact. Should you have any concerns, please reach out:
📧 support@cirrascale.com
Posted Dec 07, 2025 - 07:48 CST