KEF01 - Maintenance on UPS system UPS-A2-D and UPS-A1-C - 10/20/2025 3:00 AM CST -- 11/03/2025 6 PM CST

Scheduled Maintenance Report for Cirrascale Cloud Services

Completed

The scheduled maintenance has been completed.
Posted Nov 03, 2025 - 18:00 CST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 20, 2025 - 03:00 CDT

Scheduled

Dear Customer,

Please be advised of an upcoming scheduled planned maintenance event affecting our Iceland Data Center:


📅 Date:

10/20/2025 – 11/03/2025

⏰ Time:

03:00 AM CST – 6:00 PM CST (November 3rd)

📍 Location:

KEF01 – Iceland

🔧 Affected Services:

Improvements on high voltage feeders at FIT

⚠️ Expected Impact:

No anticipated impact.

Redundant systems will be fully operational.



What’s Happening?

Our CCS Data Center Partner will be performing maintenance to ensure continued reliability and performance of the UPS systems.

Impact

No anticipated impact to customer equipment.

UPS will be put in maintenance bypass one at a time

Redundant UPS systems will remain fully operational throughout the maintenance window.

Only one UPS system will be serviced at a time during the maintenance window.


How You’ll Be Notified:



✅ Initial Notification – Sent upon scheduling of the upcoming maintenance work.
✅ 1-Hour Reminder – A reminder notification is sent one hour before the start of the maintenance window.
✅ Start Notification – Issued at the beginning of the maintenance to confirm that the work is underway.
✅ Completion Notification ("All Clear") – Sent once maintenance is complete and all services are confirmed to be operational.

Our team will actively monitor the situation and remain in contact with the CCS Data Center Partner. Should you have any concerns, please reach out:
📧 support@cirrascale.com

Thank you for your understanding and continued partnership.

Email - support@cirrascale.com

Web - http://www.cirrascale.com
Posted Oct 08, 2025 - 23:27 CDT