MDW01 - CCS Maintenance Notification CH2 20-Q-4 (N+1) Quarterly Chiller Inspection- Date: 2026-04-30 4:00 AM- 2026-05-30 12:00 PM

Scheduled Maintenance Report for Cirrascale Cloud Services

Completed

The scheduled maintenance has been completed.
Posted May 30, 2026 - 12:00 CDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 30, 2026 - 04:00 CDT

Scheduled

Cirrascale Cloud Services Customer Customer,

Please be advised of an upcoming scheduled planned maintenance event affecting our MDW01 (Chicago) Data center:

📅 Date: 04/30/2026 – 05/30/2026

⏰ Time: 4:00 AM CST – 12:00 PM CST

📍 Location: MDW01 (Chicago)

🔧 Affected Services: CH2 20-Q-4 (N+1) Quarterly Chiller Inspection

⚠️ Expected Impact: No disruption is anticipated, but the potential exists

What’s Happening?

This preventative maintenance procedure will thoroughly inspect and verify the proper operation of the chillers, ensuring optimal performance and reliability

How You’ll Be Notified:

✅ Initial Notification – Sent upon scheduling of the upcoming maintenance work.
✅ 1-Hour Reminder – A reminder notification is sent one hour before the start of the maintenance window.
✅ Start Notification – Issued at the beginning of the maintenance to confirm that the work is underway.
✅ Completion Notification ("All Clear") – Sent once maintenance is complete and all services are confirmed to be operational.

Our team will actively monitor the situation and remain in contact with the CCS Data Center Partner. Should you have any concerns, please reach out: